What is critical chain project management
YouTube Viewers YouTube Viewers
28.9K subscribers
11,064 views
0

 Published On Jan 18, 2021

The critical chain method is a technique that modifies the project schedule to account for limited resources by adding duration buffers that are non-work schedule activities to maintain focus on the planned activity durations.


Critical chain is completed after determining critical path by entering resource availability and the resulting schedule produces a resource-constrained critical path, which is usually altered from the original. Critical chain focuses on managing remaining buffer durations against the remaining durations of task chains.